- 820 km of Key SHs - improvement
- 101 km of SHs - 4-laning (including 4-laning of Mehsana-Palanpur)
- 88 Major Bridges - reconstruction
- 16 Major Bridges - repair / rehabilitation
- 166 Minor Bridges - reconstruction
- 53 Minor Bridges - widening and rehabilitation
- 842 Culverts - reconstruction
- 443 Culverts - widening and rehabilitation
Details of the Phase works of
road widening and strengthening
component under GSHP
|
Sr. No. |
Phase |
Contract
No. |
Name of
corridor |
Chainage,
Km. |
Length |
|
From |
To |
|
1 |
2 |
3 |
4 |
5 |
6 |
7 |
|
1 |
Phase-I |
GSHP-1 |
Sarkhej-Viramgam |
11.32 |
59.20 |
47.88 |
|
2 |
Phase-I |
GSHP-2 |
Mehsana-Palanpur |
78.06 |
141.27 |
63.21 |
|
3 |
Phase-I |
GSHP-3 |
Rajkot-Jamnagar |
3.00 |
64.75 |
61.75 |
|
4 |
Phase-I |
GSHP-3A |
Bridge on
river in Rajkot Falla road |
|
|
|
|
5 |
Phase-I |
GSHP-4 |
Kadodara-Bajipura |
17.40 |
63.63 |
36.23 |
|
6 |
Phase-I |
GSHP-5 |
Halol-Godhra |
335.16 |
373.40 |
38.24 |
|
7 |
Phase-I |
GSHP-5A |
Bridges
on Goma and Karad river on Halol-Godhra |
1.78 |
123.0 |
- |
|
8 |
Phase-IIA |
GSHP-6 |
Mehsana-Palanpur |
75.800 |
138.600 |
62.8 |
|
9 |
Phase-IIA |
GSHP-7 |
Godhra-Shamlaji |
379.900 |
501.400 |
121.5 |
|
10 |
Phase-IIA |
GSHP-8 |
Ladvel-Dakor-Godhra |
18.700
90.100 |
0.500
135.700 |
18.2 45.6 |
|
11 |
Phase-IIB |
GSHP-9A |
Vadodara-Padra-Jambusar |
8.268 |
53.00 |
44.732 |
|
12 |
Phase-IIB |
GSHP-9B |
Bharuch-Dahej |
200.00 |
248.200 |
47.100 |
|
13 |
Phase-IIB |
GSHP-11 |
Falla-Jamnagar-Khambhaliya |
63.981
94.100 |
78.830
144.993 |
14.849
50.893 |
|
14 |
Phase-IIB |
GSHP-12 |
Viramgam-Dhrangadhra
& Dhrangadhra-Halvad |
58.825
126.000 |
104.263
151.500 |
45.438
25.5 |
|
15 |
Phase-IIB |
GSHP-13 |
Dholka-Bagodra and Wataman-Pimpri |
0.000
69.600 |
23.018
94.163 |
23.018
24.563 |
|
16 |
Phase-IIB |
GSHP-14 |
Olpad
Surat & Magdallat-Navsari |
9.300
12.172 |
19.200
25.634 |
9.9
13.462 |
|