Highlights of Widening & Strengthening
  • 820 km of Key SHs - improvement
  • 101 km of SHs - 4-laning (including 4-laning of Mehsana-Palanpur)
  • 88 Major Bridges - reconstruction
  • 16 Major Bridges - repair / rehabilitation
  • 166 Minor Bridges - reconstruction
  • 53 Minor Bridges - widening and rehabilitation
  • 842 Culverts - reconstruction
  • 443 Culverts - widening and rehabilitation

Details of the Phase works of road widening and strengthening

component under GSHP

Sr. No.

Phase

Contract No.

Name of corridor

Chainage, Km.

Length

From

To

1

2

3

4

5

6

7

1

Phase-I

GSHP-1

Sarkhej-Viramgam

11.32

59.20

47.88

2

Phase-I

GSHP-2

Mehsana-Palanpur

78.06

141.27

63.21

3

Phase-I

GSHP-3

Rajkot-Jamnagar

3.00

64.75

61.75

4

Phase-I

GSHP-3A

Bridge on river in Rajkot Falla road

 

 

 

5

Phase-I

GSHP-4

Kadodara-Bajipura

17.40

63.63

36.23

6

Phase-I

GSHP-5

Halol-Godhra

335.16

373.40

38.24

7

Phase-I

GSHP-5A

Bridges on Goma and Karad river on Halol-Godhra

1.78

123.0

-

8

Phase-IIA

GSHP-6

Mehsana-Palanpur

75.800

138.600

62.8

9

Phase-IIA

GSHP-7

Godhra-Shamlaji

379.900

501.400

121.5

10

Phase-IIA

GSHP-8

Ladvel-Dakor-Godhra

18.700 90.100

0.500 135.700

18.2 45.6

11

Phase-IIB

GSHP-9A

Vadodara-Padra-Jambusar

8.268

53.00

44.732

12

Phase-IIB

GSHP-9B

Bharuch-Dahej

200.00

248.200

47.100

13

Phase-IIB

GSHP-11

Falla-Jamnagar-Khambhaliya

63.981 94.100

78.830 144.993

14.849 50.893

14

Phase-IIB

GSHP-12

Viramgam-Dhrangadhra & Dhrangadhra-Halvad

58.825 126.000

104.263 151.500

45.438 25.5

15

Phase-IIB

GSHP-13

Dholka-Bagodra and Wataman-Pimpri

0.000 69.600

23.018 94.163

23.018 24.563

16

Phase-IIB

GSHP-14

Olpad Surat & Magdallat-Navsari

9.300 12.172

19.200 25.634

9.9 13.462

 

 

Bus Bay and Road Markings on Sarkhej-Viramgam Road Bus Bay : Meshana Palanpur Road
Kadodara-Bajipura Road Halol Bypass on Halol-Godhra Road